HomeLocal NewsECG has not undertaken load shedding this year - NAPO

ECG has not undertaken load shedding this year – NAPO

On Wednesday, June 19, 2024, the Minister of Energy, Dr. Matthew Opoku Prempeh, addressed an urgent question in Parliament. He stated that the Electricity Company of Ghana (ECG) has not implemented any load-shedding exercises this year. Dr. Prempeh, also known as NAPO, explained that he had been scheduled to address the question, which was submitted over two months ago. However, he was unable to respond earlier because the questioner was either unavailable or Parliament did not allow him to respond despite his availability on three occasions.

He explained that the power outages experienced two months ago were not due to a power crisis but rather unforeseen factors such as rapid population growth and increased business setups. For instance, Dr. Prempeh noted that areas like East Legon, initially planned as residential districts, have transformed into business hubs, overloading existing power lines and transformers.

He said this surge in demand, combined with an unexpected gas leak at Cenpower resulting in an instant power loss of 340 megawatts and maintenance at Amandi Power Plant, led to power outages. NAPO added that GRIDCo also requested emergency outages in some areas, exacerbating the situation.

He stated these incidents were unplanned, making it impossible for the Electricity Company of Ghana (ECG) to announce a scheduled load-shedding program. “The question has to be seen in the context that it is a question from over two months ago as an urgent question. Mr Speaker, I will proceed to answer as the utility (ECG) advised.

“…No, ECG is not undertaking load shedding as at the time the question was asked. Mr. Speaker, consumers were experiencing outages due to a number of factors that included localized outages due to overloads on lines and transformers.” “So, Mr Speaker, there was a myriad of factors that unfortunately were causing power outages in different parts at different times.

“Mr. Speaker, the reason why ECG went further to say they were not load shedding is because most of these incidents were not planned, so they couldn’t come out to say there was load shedding.” Dr. Prempeh made these remarks in response to an urgent question from the NDC MP for South Dayi, Rockson-Nelson Etse Dafeamekpor, on behalf of the NDC MP for Tamale North, Alhassan S. Suhuyini, who was absent.

Mr. Dafeamekpor asked if the Electricity Company of Ghana (ECG) had been load-shedding power and if not, why the power outages occurred. Despite his response, some Minority MPs pressed for more information on the current power situation, as the original question referred to the situation two months prior.

Dr. Prempeh maintained that the ECG is not undertaking a scheduled load-shedding program but he was ready to address any new questions when they are filed.

Source: GraphicOnline

Benjamin Mensah
Benjamin Mensahhttps://freshhope1.org
Benjamin Mensah [Freshhope] is a young man, very passionate about the youth of this Generation. Very friendly, reliable and very passionate about the things of God and all that I do. The mission is to inform, educate and entertain. Feel free to send your whatsapp messages to +233266550849 and call on +233242645676
RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -
Google search engine

Most Popular

Recent Comments

Janet Obenewaa on BEFORE AND AFTER “I DO”.
Nanayaw Frimpong on BEFORE AND AFTER “I DO”.
Nanayaw Frimpong on BEFORE AND AFTER “I DO”.
Abwaresen Joseph on DANGEROUS WOMEN TO STAY WITH
Asiedua Naomi on LOVE vs MONEY.
Ewuraa on LOVE vs MONEY.
Francis selorm Agbosu on Power of Anger
Ewuraa on Power of Anger
Ewuraba on THE POWER OF WORDS.